Hi,

We are implementing the Approve Leave Requests (V2) Fiori Application.

We have 3 Levels of Workflow based on the Custom Workflow.

When the Employee raises a Leave Request, the work item is created and routed to the proper first level approval person.

When the first level manager opens the Leave approval application by opening the tile,the

Master Detail page is displayed with the data as required.

When the user clicks on the Approve button, we are getting the message that the work item is approved, but the master page is not getting

refreshed and still shows the work item. While checking in the back end,the Work item is approved.

We are using the standard fiori application as is with the following software components.

UIHR001 100 0002

GBX01HR 600 0002

The Leave Approval is working fine with the HR Renewal based UI5 application without any issues.

Appreciate if you could provide some input to resolve this issue.

Thanks,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Urmila,

it's been a long time ago that you write this article and it isn't answered yet.

Do you got any solution for this? Because we have the same problem with the Fiori App "Approve Leave Request (V2)". We use this app in the HCM enviroment.

Regards,

Thorsten

former_member214868
Participant
0 Kudos

Hello Thorsten,

The root cause of the issue was in our custom leave workflow. Kindly check your custom Leave workflow and ensure that it works fine in any of the WD ABAP/Java based ESS applications.

Thanks,

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Urmila,

I see support package level is old.

Please check help document. App Implementation: Approve Leave Requests (Version 2) - SAP Fiori Apps - SAP Library

Regards,

Masa / SAP Technology RIG

former_member214868
Participant
0 Kudos

Hello Masayuki,

Looks like SP3 is released this month and we are on SP2 Level.

Kindly let me know if there are any notes applicable for the Leave Request Approval V2 application for SP2 which we will implement to resolve the same.

Appreciate your response.

Thanks,

masa_139
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Urmila,

Please go live with the latest Support Package.

You can search notes at SAP Note & Knowledge Base Article Search | SAP Support Portal

Regards,

Masa / SAP Technology RIG