Dear SAP Experts,
I am facing an issue. When we run cost estimate run of subcontracting material from t-code CK11n , system is not taking current PO price. We want that system take price from current PO. Please guide me how to resolve this issue.
Regards
Muhammad Umar
Hi Muhammad,
In CK11N subcontracting cost of material is generally taken from latest subcontracting Info record maintained for the material.So maintain latest info record for your material.
And also check the setting for subcontracting in OKKN valuation variant it should be 'Net quotation price.
Regards,
Prasad