on 04-20-2007 4:55 PM
In the change request management, I am in the developer phase and I created transport in solution manger and went in the DEV box and made the changes and added the changes to transport number that was created by Solution Manager. Now How do I change the STATUS from In Development to Development Completed, my STATUS options are grayed out in the STATUS button. I am not able to continue to Test phase due this problem?
Can anyone please tell me what I am exactly missing here?
Thanks In Advance.
Kumar
HIiii Kumar
First of all What you are implementing
1. Urgent Correction
2. Or Normal Correction
In both cases you have to set yr development completed from Action button not from Status button.
I hope I have answered yr question.
Feel free to ask any doubt
Sukhii
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Well, I am only testing NORMAL Correction now. Well, I do not see any action to complete the development.
I could only see the following ACTIONS:
Logon to system
Complete Procedure
Cancel Procedure
Create Transport Request
Create Task
Release Transport Request
Critical Transport Request
Test Transport
Go to Task plan
Hii
Then you have to release first Task in yr satellite system then release Request from your Solman Action...Insucessfull complition of both of these actions(Without any error & Warnings).Then you will see compleate development Action in your Action list.
If you got then dont forgot to give points.
Sukhwinder Singh
thank you for your quick repond.
First task is already released in the satellite system. When I try to release the tranports in in SOLMAN from one of the ACTIOON Release Transport Request, I get this following error.
<b>Action cannot be performed during this maintenance phase
Message no. SOCM_ACTION_LOG 024
Diagnosis
The maintenance cycle does not allow a specific action to be executed.
System Response
The system terminates the action.
Procedure
The maintenance cycle can be set by the Change Manager or the system administrator during the next or previous phase.
Additional Information:
Action 'Regular Correction: Release Transport Request' cannot be
executed during phase 'Development without Release'
</b>
Any idea?
Kumar,
I believe your problem is that you need to change phases through your maintenance cycle Task List. In general:
normal correction => phases are managed through maintenance cycle task list Mxxx
urgent correction => phases are managed through Urgent Correction task list Hxxx
Hope this helps
Henry Strange
Hi Kumar,
Once you have released your transports through the Action button, then you have to select Complete Procedure from the Action button and save.
This will change the status to Development Completed.
In CHaRM, all the status changes are driven by the action button.
Something to keep in mind is when you release your transports from the actions button, at the same time, it runs a job to delete the unused transport that it created. Until that transport is successfully deleted(which might take a few seconds) the Complete Procedure action might not change the status right away. Look at the Display messages icon on the top right-hand side for any warnings.
Let me know if this helped.
Salpi
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.