on 11-25-2015 10:25 AM
Hi Experts,
I have a situation in Integration Directory, where I edited one communication channel, The new change got saved but when i tried to activate it nothing happened and the object remained in In Process status. The object is not getting activated. When I try to edit again and save, a pop up appears with the statement "Change list specified is already closed. Status: processed; GUID: XXXXXXXXXXXXX".
I have checked in administration and there is no lock with my ID for that object.
I have done clear SLD Data Cache in Integration Directory.
I have also checked the change list and that object is not under open or closed change lists.
Could you please suggest on how to activate the communication channel.
Thanks & Regards,
Treya Dasgupta
Hi,
There must be some kind of version conflict on the object in changeLists.
1- Work around - got to NWDS and creat custom changelist and try editing the channel in that changeList. Please let me know if it works
2- Also to confirm the conflict try creating/copy object of channel with exactly same name or try deleting it once.
Regards,
Vikas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Treya,
Check this note with your basis team 2096265 - Analyzing database inconsistency with Integration Respository/Directory objects
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is there an unresolved conflict pending for the object?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.