on 11-20-2015 3:01 AM
Hi Experts,
I have an issue with the UOM for safety days' supply. I have already configured the following
in Planning Area - Safety Days' supply -> UOM is not ticked
in table /SAPAPO/TSPAPLOB, I changed the UOM Plan to '10'
in Planning Book, decimal places for this KF is '0' (Value for UOM table is not selected)
Once I open the planning book, the Safety Days' Supply is in "D" however, when I tried to load a selection profile, the unit of measure changes to 'KG'. I have not inputted any data in this key figure so would like to ask what else could I have missed?
Thanks in advance.
Ria
Got the fix. Must also maintain /SAPAPO/TSPAPLOB UOM Plan 10 in PLOBID 9AMALO