on 11-18-2015 7:49 PM
Gurus,
We've a need to fix peg production orders, as they get CIF'd over into APO. We tried to use the Planning Procedure' Create/Change Production Order in the OLTP system event to trigger the action Start Prod Heuristic Immediately (& added the fixed pegging setting onto the product heuristics configuration - SAP_PP_002) to no avail. However, if I were to go into ECC & say, add a long text & save the Prodn Order, the Product Heuristic kicks in immediately in APO & the fixed pegging is activated on it. Note that we set the conversion indicator on the Planned Orders in APO & the production orders are created from ECC.
We are looking for some sort of trigger (without any system enhancement) with which we could kick off the SAP_PP_019, specifically for the incoming Production Order.
Any clues?
Cheers
Hi Andy
please check setting of heuristics SAP_PP_019 where you can place filter by categorys
where you can kickoff production orders category for running in BG for heuristics SAP_PP_019
regards
Viender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
1. While I could use this setting, I do not want a job to keep running, say every 5 mins.
2. I'm looking to see if there is any event that I can use in APO (Create/Change Production Order) to kick off this job when the Production Order CIF shows up in the APO system.
Thanks for your advice
Cheers
Hi Andy
In planning procedure you can select event C1 (create or change production order in OLTP) set action
as NO ACTION .
But as per my knowledge there is no link in between planning procedure and Heuristic BG Job running .You may need to restrict at Heuristics settings level only . let check any other expert can help you
Regards
Virender
Expert Virender,
I agree with you that there is no way to kick off a b/g job with the event on the Planning Procedure. Not sure if you've read my initial post completely, but we did try the Planning Procedure setting to call the Product Heuristic on the CIF of a Production Order into APO & by activating FIXED PEGGING on the prod heuristic. However, the Prod Heuristic wouldn't get invoked & hence no fixed pegging. What do you think setting NO ACTION for this event will help with?
Cheers
Hi Andy,
Yes, you can use SAP_PP_019 for pegging and please remember before MRP run (APO) you have
to delete the pegging relationship by using SAP_PP_011 and rerun the SAP_PP_019.
Br,
Sriniwas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.