on 11-18-2015 8:51 AM
Hello there,
I am facing with an issue on the sum execution phase.
I am applying the SPS06 on my NW Gateway 7.40 SP02, all the phases were succeeded but during the execution sum stucks on the error below:
2EETW000 key field /UI2/NWBC_CFG_NT-CLIENT contained teh value '001' : key field /UI2/NWBC_CFG_NT-CLIENT missing, key is truncated.
Does somebody have an idea ?
Regards.
Hi,
Please go through below sap note that explains the issue.
2037662 - SAP_UI 7.40 minimal installation requirements
Regards,
Prithviraj.