on 11-16-2015 9:47 AM
Hello
I need to define both: day and hour time granularity for Non conformance and Production operation .
I need to know if this issu impact performance or not ?
Thank you
Houssem
Hi!
What do you mean by "impact performance or not"? If you assign a time granularity to any category, this way you ask the system to execute summarization for this category based on the specified granularity. Each granularity is addressed separately during a summarization round for the category. Thus the more granularities you assign, the more time it will take to summarize.
Regards,
Sergiy