unable to create delivery from CNS0

former_member210342
Participant
0 Kudos

HI All.

Here is query.

I have a procured a material through project with procurement type (reservation + requisition for WBS element)

Now, material is procured and it is showing in reserved quantity in MMBE with account assignment as network(right click on stock -->reservation).

as per process , once I will create delivery , it will be removed from stock,

But while creating delivery through CNS0, I am not able to pick material( 0 qty available)

Please help and tell cause of it .

Any other info required let me know please

Thanks

Rahul

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Rahul,

This question was previously answered

Look into the thread

http://scn.sap.com/thread/907163

Hope this helps

Regards

Vittal

former_member210342
Participant
0 Kudos

Hi Vittal,

It is happening in one project.. Few wbs are missing.others are visible.

If you can help in same

Thanks

Rahul

Former Member
0 Kudos

Hi Rahul,

The WBS are missing in Project builder or at the time of delivery?

former_member210342
Participant
0 Kudos

Hi Vittal,

It is missing from project...and even there is no old data exist even in tables also.

PROJ and PRPS also showing no value found.

Earlier it was.

now nothing..even a single report have data for missing wbs

please help ..........

Thanks

Rahul