on 11-11-2015 4:17 AM
Hi Team,
I have created a Planned Order in the APO system using the transaction /SAPAPO/RRP3. This Planned Order has a Resource visible in the "Resource" column. When I convert this Planned Order to a Process Order, the Resource for this Process Order is no longer visible in the "Resource" column.
Could you please help me in resolving this issue?
Thanks in advance for the help and for your time.
Thanks & Regards,
Srikanth.
Hi Srikanth,
Make sure there is an active integration model for the Resource. If there is not, the operation will be filtered from APO once you convert the PlOrd into Process Order.
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krovvi sri
Before converting to process order .check your are planned order is in allocated status . Any Heuristics you are running for scheduling purpose after generating planned orders .
Regards
Virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.