I have trouble about shifting activity, i try to imitate function ms.project automatic reschedule.
Act Start Finish
Activity10 02.11.2015 03.11.2015
Activity20 04.11.2015 05.11.2015
Relation between activity FS, Activity 20 as successor.
I try to extend finish date activity10 through CJ2B to 10.11.2015.
why activity20 did not reschedule to 11.11.2015(Start) 12.11.2015(Finish)?
please can someone help me to give me solution, what should i do?
best regards,
michael a
You have selected "WBS determines the dates". So the dates on the assigned WBS are passed down to the activities and they have to work within those dates. Strange things can happen if the dates aren't aligned.
Is there a reason you wan this? Otherwise change to strict bottom up planning.
I also usually use backwards scheduling as the finish date is more critical that the start date.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.