on 11-04-2015 5:47 PM
HI Gurus,
I'm puzzled here, as I have done everything to activate AVAC for all my projects, but it only actvates in 1 scenario of project creation (and fails for the other).
Scenario - 1
CJ20N I create a project structure without Network header and activities. release WBS. Save
IM52 Distribute budget to it
CJBV Activate AVAC
CJ20N Add Networkheader to project, add Network activity, add material compoment for price that is valued over budget.
Release Network header + Network, Save.
In this scenario I get my Error message saying that I'm over budget
Scenario - 2
CJ20N I create a project structure with Network header, activities and material component priced over budget straight away
IM52 Distribute budget to it
CJBV Activate AVAC
CJ20N Release All: WBS, Networkheader + Network, Save.
In this scenario I succesfully raise a Purchase Requisition above budget.
Please can some one help me to understand why Error message is not showing up in Snerio 2.??
here is my config
Hi Daria,
It seems Assigned Value is creating trouble, pls let us know if "assign fund in the plan" checkbox active or not in OPSV config.
Check SAP note 783161 regarding the role of assigned value and availability check
In Scenario-2, assigned value may not getting updated correctly, check note 1424698
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Everything is based on configuration.
What is wrong about material reservation? I do not remember if GSAP has valuated project stock or not, but the earlier you can capture potential cost the better it is...
If you consider that balance sheet items are not relevant for AVC you can exclude those accounts in OPTK.
Hi Daria,
Can you please check config in
SPRO-- PROJECT SYSTEMS -- COSTS -- BUDGET -- define tolerance limits.
whether your budget profile has been mapped to tr.grp field set to ++ or individual objects ( like PR , PO etc) . If it is individuals objects check whether it is mapped to PR.
If you feel above config is fine, then check
SPRO-- PROJECT SYSTEMS -- COSTS -- BUDGET -- specify exempt cost elements.
Check cost element used in PR is exempt here in this config.
Thanking you
Vengaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.