Regarding QASH table

0 Kudos

Hello ,

I am  creating an inspection  lot but entries are not getting filled in table QASH .Though all master data seems to be proper like in control indicator SPC characteristic has been selected , sampling procedure used is of fixed sample type .But still when I am creating an inspection lot entry is not coming in table QASH?

Are there any other condition which leads to an entry in table QASH ?

Please suggest .

Regards ,

Sujit Prasad

Accepted Solutions (0)

Answers (2)

Answers (2)

busyaban7
Active Contributor
0 Kudos

Hi Sujit,

Anand is right as I also feel that there must me something missing in your setup, if this is first time you are trying to implement SPC functionality.

Please can you also check if you have maintained Sampling Procedure => Valuation Mode as 'SPC Inspection" as suggested by Do-Wook Kim in the thread http://scn.sap.com/thread/2138475?

Thanks,

Arijit


anand_rao3
Active Contributor
0 Kudos

If you have set the SPC criterion then it should reflect. Do you see any records in QGC1 for the same inspection lot? If not then something is missing in inspection plan. I would suggest to recheck the sampling procedure used, control chart type and SPC criterion have been set properly.

Anand