on 11-04-2015 6:51 AM
Hello Experts,
I need some changes coming through from ECC for an InfoObject to reflect in BW system. We already have all the data into PSA. Please help if the below approach is correct or has some bottle necks/ concerns:
- Load full request from PSA to DSO
- Activate request
- Execute ACR for our infoobject
- Delete the dull request from DSO so that the other delta requests in our DSO do not get disturbed.
Can you please help and suggest if this is the right way to go?
Thanks in advance!
Sheen
Hi Sheen,
Are the Keyfigures additive in the DSO, else the final step can be avoided.
You can load the master data and then load data to the DSO , and activate it.
Regards
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Sheen,
First load data to master data info object and run ACR.
Later load data to DSO and activate it.
Delete data from DSO is not needed.
As DSO its over write function. so deletion is not required.
Actually why you want to delete full load request from DSO?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sheen,
ACR is basically to keep the master data upto-date so that it can generate SID's while you load the transaction data.
What is the load you are going to do from PSA to DSO ? Transaction data ?
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.