on 11-04-2015 4:51 AM
Hi,
Can someone please help me determine if SM36 is the correct transaction to add the schedule status to a plant maintenance work order without using a scheduling tool such as MRS?
Hi Clive,
If this is a system status, then Scheduled status can be set using CM25 transaction where you assign a work center to a work order and then dispatch.
Thanks,
Tajinder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Clive,
Some questions:
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.