How to see the planned requirement and actual consumption of material in Process order?

Hi SAP Guru,

In Process order, I can see the planned and actual quantity for material in COR2/COR3.

Is there a way to see the info for a bunch of process orders in order to see the variance?

Thank you,

Sally

replied

Hi Sally,

You can use COHVPI. Once you run the report, if you don't see both quantities, you can add more columns.

Also note that this question should be moved to SAP PP space.

Kind Regards,

Mariano