Duty on Sub-contracting Process

Hi Experts,

Need your advice. We buy Material A from a China Vendor, one of the component that goes into Material A is supplied by us. The requirement is while getting the assembled product which is Material A, we need to pay duty on it. Duty is a % calculated on material cost including the component supplied by us. Once we receive Material A, we need to reduce the inventory of the component that is consumed in Material A

The question is how do we handle the entire process in SAP and also the inventory reduction of the component.

Thanks in advance

Jen.

Former Member
Not what you were looking for? View more on this topic or Ask a question