on 11-03-2015 8:47 AM
Dear SAP experts,
We are assesing forecasting feature in MM-CBP (Consumption Base Planning). When testing I feel odd that I cannot re-execute the forecast in the same period. I have search in SDN and many has proposed to intialize field Initialization in forecasting view. I have followed this advice. After executing the forecast on perion 11, I get the forecast result. And then I change the material master and change the initialization from 'X' (by system) to blank. After that I try to run the forecast again in MP30. In MP30 screen I see that the initialization does show blank. After I click execute, I see that the initialization is set back to 'X' and I got the same error:
Msg no PR135
So how to re-execute forecast in the same period?
Best regards,
John
See the logic in FORM check_wiederholprognose. of ABAP MM61WFAR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
10 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.