Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

copy planned cost to estimated cost in work order

hi experiment ,


i have requirement to copy planned cost to estimated cost in the save  work order  please help me to get user exit and function module to get this

i have add this requirment and deleted because it a same in another post but i have to mention here http://scn.sap.com/thread/2079395?start=0&tstart=0

to know is the reply in this post is true or not please advise

best regards Sadin

Former Member
replied

Sadin,

I know it can be done in user-exit IWO10009 because we have done it on a previous project

What you need to do is:

  1. In IWO10009 you need to force a "Determine Costs" function. Get your ABAPers to debug the way the standard program does this via the IW31/2 button (looks like a calculator on the order header).
  2. Then you need to retrieve the cost data from memory - it'll be the one of the PMCO tables in probably in program SAPLICO1.
  3. Put the data into the Estimated Cost field (CAUFVD-USER4). Note this can be done before or after release.

PeteA

3 View this answer in context
Not what you were looking for? View more on this topic or Ask a question