There is a requirement to create one PR against one reservation created from Maintenance Order. For more details, if there are multiple reservations or requirement from different sources (maintenance Order or manually or because of re-order point), one PR should be created against each reservation.

This is needed later on to convert one PR to one PO so that vendor can bundle material to that particular location and not to Warehouse.Could you please advise how this can be made possible in SAP?

Regards

R

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

On the standard system this is not possible. See my answer on thread .

The following document provides an alternative using BAdI MD_ADD_ELEMENTS .