SPAM phase stuck in "tp successfully connected"

Dear,

We are upgrading the SAP_BASIS software component SP11 for production, the upgrade went well for development and quality system, But in production the SPAM phase got stuck in "tp successfully connected" screen, after this no process is running,checking the SLOG we are getting error

"WARNING: \\sapmnt\trans\tmp\PRD_U.PRD is already in use (170), I'm waiting 2 sec". As per another note we deleted PRD_U.PRD file, but still the phase is not moving forward.Any advice.

Former Member
Former Member replied

Dear Manu,

There is no error, the problem is happening in the RDDIMPD background job, its not scheduling properly.