Hello Everyone,
I am new to SAP PP area. In our system for other plants and storage locations when production order is getting released the TR gets created and when they go to LM01 transaction they are able to pick the order without any issues.
I have created 2 new supply areas for returns and repairs. I have also created conrol cycles. Now when the company creates production orders for returns or repair plant and release them, system is not generating TR.
Am I missing any configuration steps ?
Thanks in advance,
Khushbu.
Hi Khushbu,
Hope the PSA (production supply area is maintained in BOM or in PV in material master).
Also please do the OMK0 setting - Define replenishment control for storage type.
Thanks
Kishan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kiran,
Thanks for replying. I have made the settings that you have mentioned but still when I go to LM01 transaction to pick the production order I get a error message that "Open reservation for order does not exist". I can only pic the orders through MIGO not with the RF gun.
How to resolve this.
Thanks,
Khushbu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
You must create a production scheduling profile on transaction OPKP and make sure that the proper value is set for the field "WM Request". After that, this profile must be assigned to the material master.
Regards
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Khushbu,
Check whether below steps are in place?
1.Production supply area created in PK05
2.Control cycle defined - Must set the WM request flag at the production control level, if you want the material staging for production orders to take place automatically and If you want to use automatic staging, it is essential that the materials used in connection with this interface are assigned to a production storage location and contain a production scheduler
3.Check whether PSA is assigned to your Workcenter
4.Production scheduling profile setting for WM TR request.
BR
KK
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.