Hi all,

I am bit new in SAP APO

I am trying to CIF material from ECC to APO system. I am getting the error "No Supplying plant defined for the product prod_01"

I have already transferred 'plant' through CIF and it is successfully done.

I have used following two steps:-

  Step 1:- CFM1 for creating integration model.

  Step 2:- CFM2 for activating integration model.

Can anyone please help me with the issue?

Thanks in Advance

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member213836
Active Participant
0 Kudos

Hello,

Root Cause:

1. This is a bug in SAP. Check the OSS notes and related correction instruction.

          a. 1292729

          b. 1263714

          c.  1397763

Regards,