on 11-02-2015 8:17 AM
Hi SAP Experts,
Asking for your help on the set up of safety stonk planning in CTM
We would like to use safety stock and below are the parameters maintained.
1. Take Safety Stock into Account (3) is selected in the planning version
2. Safety Stock Method SZ and Safetiy Day's supply is maintained in Product Master
3. CTM:
Supplies -> Build Up safety stock (Consider supply shortage, stock is available) -> Consider Safety Days' Supply (always consider) is selected, but the safety days supply is still not respected.
Thanks! Sincerely, Ria
Hi Ria,
It seems the first setting itself is not correct that is in planning version as 3. If you check F1 help of this field it clearly states CTM ignores the "Build up safety stock indicator" in CTM profile for 3. The below is an extract from "performance assistant (F1)" for this field:
Consider Safety Stock Requirements in SAP liveCache
I would suggest you to cross-check this setting once again and switch to "2 - Consider Virtual Safety Stock Elements". Thereafter check the results and let us know if you still face an issue.
Regards
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rahul,
Thank you so much for your reply It somehow worked. But the safety stock is way below what I have provided. Btw, am using aggregated planning. If such is the case, should I put the safety stock in the product header or in the FGs (which are members of the product header). Currently, am maintaining it in both.
Thank you very much for your help. Sincerely, Ria
Hi Rahul,
Safety stock should be planned on the members. But CTM is planning at header level. So am thinking of maintaining it only at the header. Will this have the same correct safety stock. Am thinking of just using heuristics with capactiy planning. Still using aggregated planning also. but safety stock is the same. not working as expected.
Sincerely, Ria
Hi Ria,
As I mentioned above please don't mix issues (SCN rules of engagement). Your initial situation was that safety stock not even considered which you confirmed is now working. Please close this thread and open another discussion with some screen shots example what do you see with demand and supply w.r.t. days of supply.
We will try to help you there also.
Regards
Rahul
Hi Rahul,
Apologies for the confusion. I thought it is working but it is not as am not getting the correct day's supply. It just so happened that the number of days is lower now than before. Safety Stock method is SZ, so the day's supply should be the same as the product master. anyway. will just close this and will raise a new one.
Sincerely, Ria
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.