Sunday Premiums In Time Schema TM00

Dear Gurus,

I need your help I had the following request from my company; to be in the time schema, I am using a copy of TM00

  • If employee working on a Sunday give overtime/premium at 2 for the time worked.
  • If employee is working on a Public Holiday give overtime/premium at 2 for the time worked.
  • If employee is working night shift give half his daily pay extra per night.

I tried using table V_T510S and V_T555Z for Sunday and Public holiday but this is not working well as the overtime payment is provided for the planned work and not the actual hours worked.

With regards to the night shift I was planning to use the same logic but would appreciate more ideas. I would appreciate different solution on way forward how to solve this