Hello Gurus,

Our business has deleted the standard cost estimate and again created new cost estimate for the same material. Now when performing goods issue to the existing orders the total material value is considering as variance.

There are more that 100 orders to reverse the goods issue, manually to correct the variance it takes much time so please suggest if there is any alternative way to reverse the same.

Thanks in advance

Regards,

Kiran