Laytime and Demurrange Calculations

HI

If Freight contract is set up with Lay Terms and Demurrange conditions maintained in the freight contract and Nomination is created referring the freight contract, can we see the Laytime and Demurrage in the nomination based on the scheduled quantities before actual events are recorded?

Where in the Nomination (which tab at header/item level) is this visible?

Sriram

Former Member
Former Member replied

Dear Sriram,

O4NM >> Nomination >>  Goto >> header >> Laytime calculation , in the same way  item >> Laytime calculation is the path to view the details.

Thanks,

Naresh.