I have a scenario where i will get a route from an external planning system through PI, and sometimes the operations can be in different places, in that case a new operation - "TRANSPORT" has to be added between the actual operations.
Now upon receiving this data, a planned order has to be created with the extra operation, we have been trying to achieve it by using BAPI_PLANNEDORDER_CREATE, but are unable to insert the extra operation, the list of operations gets picked up from standard.
Can anybody help me with this.
There is no BAPI to insert a new operation on a planned order. In fact, planned orders will only have capacity requirements on table KBED and there is no actual operation, such as there is on a production order.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.