cancel
Showing results for 
Search instead for 
Did you mean: 

Plan start and end date on test case level

Former Member
0 Kudos

Hello,

I am New to solution manager. I have the questions, if it is possible to assign plan end date on test case Level and tester could see which one to be executed when.

The test package coontains many test cases With different start and end date.

Please help.

Best Regards,

Routima

Accepted Solutions (0)

Answers (3)

Answers (3)

bernd_honsa
Explorer
0 Kudos

Hi Routima,

another opportunity is that you use the test case priority. By the test case priority the tester will know which test case should be executed first in the time frame of the test package.

The functionality of "test sequences" could help but you need to know that you can't execute test cases in the middle or end of the sequence before the predecessor was executed successfully. Another disadvantage of test sequences is that you can only assign one tester to one test case in the sequence.

Kind regards

Bernd

Former Member
0 Kudos

Hi Routima,

>and tester could see which one to be executed when.

You can use "test sequences"  inside of test packages to adress single test cases direct to testers and inform them by email for test readiness.

Kind regards,

Christoph

Thomas_S
Advisor
Advisor
0 Kudos

Hi Routima,

no, such a functionality does not exist.

You can only set this for testpackage level.

Regards,

Thomas