Hello,

Could you please help me in understanding based on what logic delivery date in freight service PO is determined ? The PO which is generated from shipment cost document. Searched but not getting any thing solid.

Regards,

Vivek

Accepted Solutions (0)

Answers (2)

Answers (2)

moazzam_ali
Active Contributor
0 Kudos

Hi

What is your date type in PO? Is it M, D or W?

Usually we make it M and system takes current month and fill this automatically. I never came across such requirement where this is W or D.

Thank$

former_member188914
Contributor
0 Kudos

Hi..

Its W. Is this standard SAP ? If i want this date to be next week(from current week), how can I control this ? Actually, we have issues with PO delivery dates. We do not want them to be in past at any cost. Since this freight PO has doc type NB so we are afraid this might be affected too because of any config change or Code change. What I see is that in freight service PO(generated from shipment cost) delivery date is first day of the week and PO creation date can be the last day of the week. In this case, delivery date is less the PO creation date.

Regards,

balaji_ganesan2
Contributor
0 Kudos

Hi Vivek,

Could you please confirm whether you are mentioning about this field EKET-EINDT on how it's determined during the creation of PO from SCD.

Thanks,
Balaji

former_member188914
Contributor
0 Kudos

yes.. this is exactly what I am asking .