PO line item not amendable in MIGO 411-Q

Former Member
0 Kudos

Hi All ,

Requirement is to give PO number and line item while doing MIGO 411 Q

i could manage to bring PO in editable mode in MIGO 411Q via doing changes on OMJJ  but  same way couldn't work out for making PO line item amendable in 411 Q- MIGO  and showing error

Appreciate your suggestion to achieve this  PO "Line item "amendable in 411 Q

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Prasoon
Active Contributor
0 Kudos

Hi,

   There is no option as of my knowledge. In OMJJ - field selection for 411 movement, try to add EBELP field - system will show the details!

Regards,

AKPT

Former Member
0 Kudos

Thanks for response Prasoon ,

I have already tried to add EBELP  in omjj 411 but system shows error because this field not existing in given list

do i need to mention field EBELP in some other T-code then hope can overcome this error and can add here



Former Member
0 Kudos

Any Comments plz

Prasoon
Active Contributor
0 Kudos

The message shown in the screenshot clearly answers your question. There is no other option as of my knowledge.

Regards,

AKPT

Former Member
0 Kudos

411 Q movement type takes the material from Q stock to non-Q stock.

Why do you want to do this movement with a reference to a PO?

As far as I know they have no logical connection.

Former Member
0 Kudos

Hi Arda ,

Yes by this transaction  project material transfer to own stock  and requirement is for each line item price gets picked automatically the way PO was created for these line item.

To achieve this am able to give reference of material and PO but cant give PO line item reference as its still in display

Suggest how to make MIGO 411 Q PO line item in amendable mode

Right now situation is as below

Former Member
0 Kudos

Hi There ,

Any suggestion ?