Inconsistency found in MRP created PR release date

Hi Experts,

We use MRP for creation of all PRs. The flow goes this way.

Create PM order -> enter material quantity in PM order (say qty 1) -> Run MRP  -> PR gets created based on the requirement in the PM order for qty 1.

The problem or the inconsistency that we observed in one of the PR which was created was the release date of the PR was not correct.

The PM order was created on 25.09.2015 and material was added on 28.09.2015.the MRP was run on next day and so PR got created on 29.09.2015.

The basic start date of the operation in the PM order was 27.09.2015 and basis end date was 30.09.2015.

I have no clue with this dates in the PM order ,how can the PR dates be:

Delivery date as : 10.01.2016

Request date as:  29.09.2015

Release date as :  20.12.2015

Plan delivery time is 21 days

GR processing time is 3 days

The above data u see in the Quantities/Dates tab of the PR

Need an expert help on this senario

Thanks in advance.

Looking forward for a reply in this