Dears,

Please i want to handle the cancaletion of Po release by sending mail to the initiator but it doesn't work.

I make each tasks TS20000167 & TS20000168  As general tasks

and use AC20000027 in TS20000166 to get the approval and it works fine and it transfers from approval to another approval secussefully


but when i cancel it excute the TS20000168 not TS20000167 .


Note : i copied the standard WS20000075 .

i searched but i cant solve this issue

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Layla,

When you cancel a PO, you will have to check which event is getting triggered in SWEL transaction.

I think, in your case SIGNIFICANTLYCHANGED event of BO BUS2012 is getting triggered when you cancel a PO released. I think this is as per standard functionality.

You will have to check the standard functionality first. It seems RESET event is not used when you cancel the PO release.

Thanks & Regards,
Tejas Asodekar

former_member201570
Active Participant
0 Kudos

Hi,

Please check the outcome of  Task TS20000166.

as of now you are using all standard tasks ( 3 tasks ) , where you did changes in workflow ?

regards,

shamsudheen

Former Member
0 Kudos

i didn't change in the workflow i just activate the binding and assign the rule .
this the outcomes of TS20000166

former_member201570
Active Participant
0 Kudos

Please run SWU_OBUF and make a try

regards,

shamsudheen

Former Member
0 Kudos

It doesn't work

Former Member
0 Kudos

Hi,

Please try following.

  1. Use standard workflow and check cancellation functionality in that.
  2. If worked,Copy again into new template.Don't use the custom one copied already which is not working.(Go for new copy)

Check Work item linkage in swe2 t code.