on 10-26-2015 11:37 AM
Dears,
Please i want to handle the cancaletion of Po release by sending mail to the initiator but it doesn't work.
I make each tasks TS20000167 & TS20000168 As general tasks
and use AC20000027 in TS20000166 to get the approval and it works fine and it transfers from approval to another approval secussefully
but when i cancel it excute the TS20000168 not TS20000167 .
Note : i copied the standard WS20000075 .
i searched but i cant solve this issue
Hi Layla,
When you cancel a PO, you will have to check which event is getting triggered in SWEL transaction.
I think, in your case SIGNIFICANTLYCHANGED event of BO BUS2012 is getting triggered when you cancel a PO released. I think this is as per standard functionality.
You will have to check the standard functionality first. It seems RESET event is not used when you cancel the PO release.
Thanks & Regards,
Tejas Asodekar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the outcome of Task TS20000166.
as of now you are using all standard tasks ( 3 tasks ) , where you did changes in workflow ?
regards,
shamsudheen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.