Did you mean: 

how to move the objects of IR and ID to Production

Former Member
0 Kudos

hi

i have done a file to file scenario and i have a doubt of how to move it to the prodn

plz help me out

(how to move the contents of SLD IR and ID to Production)

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Jaya,

This is very much possible, all that you have to do is, in the SLD, define transport targets. that is which Dev/ QA system corresponds to which production system.

Please go through this help link and get to more on this...

http://help.sap.com/saphelp_nw04/helpdata/en/93/a3a74046033913e10000000a155106/content.htm

Also have a look at this option of transporting using File System...

http://help.sap.com/saphelp_nw04/helpdata/en/a8/5e56006c17e748a68bb3843ed5aab8/content.htm

Regards,

Abhy Thomas

Former Member
0 Kudos

Hi Jaya Krishna,

you can transport objects using 1)File or 2)CMS mechanism,but CMS is the easy way of trasporting XI object from Dev to QA or PROD

please check this links

For SLD:

https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/9e76e511-0d01-0010-5c9d-9f768d64...

using CMS:

https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/f85ff411-0d01-0010-0096-ba14e5db...

I think these are the best docs for transport.