There is no operation number selection in Capacity leveling

Hello, experts.

Question is related to PS networks by operation capacity leveling, I found, there is no operation number selection in Capacity leveling.

We have the neccesity to do leveling for networks by operations. There is sort rule for operations by one parameter. This parameter is calculated during project scheduling. We should do capacity leveling for first scheduled by parameter operation, then do project rescheduling for parameter recalculating. Then do operations resorting and do capacity leveling for next operation and so on. We have EHP7 installed in our system. This is story.

Network number and operation number of network must be selected in leveling. I've created multi-set ZSPPNW4. I use few basic sets for operation number just in case. Then i've created selection profile on base of multi-set. Then i've created overall profile on base of selection profile.

Then i run transaction CM25, select created on last step overall profile. I've got in selection screen order number field only.

Do you know why no operation number field in selection screen? What i do wrong?