Waste handling

Hi,

We have a process were waste are generated during the production process but are not measurable at each production order level.

Waste are accumulated at one place and after one week stock are brought in system through 501 mvt and then one special production order is created which have recursive BOM and material good receipt and good issue is carried out at confirmation.

Please confirm whether their is some other alternative for this process. As using 501 mvt is very risky.

Regards,

Sun

Former Member replied

Hi,

Yes, T code is CO07.

1. In that you have to keep material blank.

2. Enter delivery qty and UOM.

3. Click on component detail add waste material code with -ve qty.

4. D production order confirmation ( In case back flush is active then check documented goods movement in confirmation screen , waste material with mov type 531 is available).