scheduling in the past

Dear Expert ;

I want to allow the scheduling in the past only in LTP.

I maintain scheduling type as backward 365 days ( in OPU5) on my scenario but it does not work .

so I add start in the past in "  paramter for determining the basic dates" it work in my scenario and also in the real time ?

I just want this option in LTP .

any help?

Former Member
replied

Hello,

You can define the the order date in past in MRP group  in OPPR and then you need to use the BAdi like MD_CHANGE_MRP_DATA to exclude this setting fro normal MRP

You can find more information about the BAdIs available on MRP on the following document:

BAdIs for MRP

Best Regards,

R.Brahmankar

0 View this answer in context

Helpful Answer

by