CK40N Getting Error

Hi Expert,

While Doing Costing , we do not want to consider 168 Material which is already in active.. and does not have BOM, that's why i want to consider only Active Goods. even i selection Screen Excluding as well Deletion Flag for those 168 Material. but again and again while do Costing RUN it was showing..

we do not want that 168 i.e Inactive Material .. we want those active and system showing correct costing because of this , we are stuck. how to Ignore that 168 Material i.e Inactive. in CK40N

See the screen shot in attachment.

Thanks in Advance.

Kind Regards

Pranav

CK40N Error.JPG (111998 B)
replied

Hi, goto MM17 field MARC-NCOST set to X to exclude materials permanently from costing run.