We have a work-in-progress production order which has the following status

REL PRT PCNF PDLV PRC GMPS

But the target cost for goods receipt is still zero. Is that normal? What's missing to get this value? I have tried WIP calculation and variance calculation but it doesn't change the target cost column

milk

Former Member
replied

Hi Mike,

Yes, you can have a test. And please also make sure there is a Valid Standard Cost Estimate when you execute variance calculation.

Best regards,

Jason