Quality stock not included in Planning

Hello all,

I have a stituation  where in  the  MD04, the net planning does not count in the Quality stock.

I earlier checked the OPJJ - under PP checking rule, where "Include Quality Insp stock" is ticked.

also in OPPQ - only the stock in transfer is ticked.

Could you please let me know if there is any settings else where, the stock moved to Quality stock is also taken as available during Net requriement planning. Thanks

Regards

Former Member
replied

In addition, if you are working with an HU-managed storage location, inspection lots are not displayed on transaction MD04. In this case, the quality inspection should be added to the total stock. If this is not happening on an HU-managed storage location, the following note should be implemented:

2023197 - MD04: Inspection stock missing from HU-managed storage loc. II