10-22-2015 1:35 PM
Hi experts;
I need to activate the PSM for the purpose of Fund Management to recruit the Budget.
I followed threads on the forum and they are very helpful, they guided me almost to each step supported with t-code to do such task but at the point to activation for the IS-PS from BF11 in order to later active the ES-PS from SWF5.
That as far I understood and made, then at time of activation of the IS-PS from BF11 the Activation CHECK BOX was deemed and not able to tic it to activate the component however else components are subject for activation and the screen is set on the CHANGE mode not DISPLAY.
So can someone kindly guide how to do that please?
Thanks in advance;
Best regards;
Ahmad Mahmud;
10-23-2015 9:16 AM
Hello Ahmad,
Find some information below:
See SAP Note 544035 - PSM Functions Not in Menu or IMG.
Make sure all authorizations are granted: If you need to run RFFM_ACTIVATE_BCSETS again, note that to execute the program, the user profile must have authorization for authorization object S_BCSETS activity '07'.
For transporting SFW settings you can create a transport as explained in SAP note 908007 in your development system.
Bear in mind that with this option all SFW settings are transported.
Additional information in these notes:
719694 Activating BC Sets in the production system
855959 Activation of Extension Sets via SPRO not successful
2004225- Switch Framework Activation of Enterprise Extensions Fails in Productive System due to BC Set Activation Error
best regards
Mar
10-23-2015 9:16 AM
Hello Ahmad,
Find some information below:
See SAP Note 544035 - PSM Functions Not in Menu or IMG.
Make sure all authorizations are granted: If you need to run RFFM_ACTIVATE_BCSETS again, note that to execute the program, the user profile must have authorization for authorization object S_BCSETS activity '07'.
For transporting SFW settings you can create a transport as explained in SAP note 908007 in your development system.
Bear in mind that with this option all SFW settings are transported.
Additional information in these notes:
719694 Activating BC Sets in the production system
855959 Activation of Extension Sets via SPRO not successful
2004225- Switch Framework Activation of Enterprise Extensions Fails in Productive System due to BC Set Activation Error
best regards
Mar
10-25-2015 9:23 AM
10-25-2015 9:26 AM
10-25-2015 9:26 AM
10-25-2015 12:35 PM
Hi Mar Novalbos;
I have a question regarding the activation of the BC set.
Fund Management is a cross-client. So if it is activated on a test client on the QAS. will it affect the functionality and transnational documentations?
Thanks in advance;
Kind regards;
Ahmad Mahmud;
10-23-2015 4:37 PM
10-25-2015 9:21 AM
Hi Osvaldo;
Thank you very much
Actually I've read it and it is very helpful indeed and now i am waiting for granting the authority to be able to activate the BC set.
Regards;