Hi All,

I want to restrict manual planned order creation at Material level.

I have tried using Plant-sp.matl status in MRP1 view, but this only restrict process order creation and does not have option to restrict manual planned order creation.

Kindly provide suggestion.

Thanks you..

Accepted Solutions (1)

Accepted Solutions (1)

former_member185450
Active Contributor
0 Kudos

Hi,

Please coordinate with your security / Basis team to remove the authorization for MD11(Planned order creation) / MD12 (planned order change) transaction codes for the desired people

Regards,

Venkatesh..

0 Kudos

HI Velmurugan/ Venkatesh,

thanks you for suggestion.

We can not implement this option as we are using MD11 in custom transaction. Another thing is client  just want to restrict planned order creation depends on business requirement for specific material for certain time.

thanks you.

marianoc
Active Contributor
0 Kudos

Hello,

In this case,  since you are using a custom transaction you have multiple different options to do it in your program. Talk to your programmer and modify the program in order to restrict it.

Kind Regards,

Mariano

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Another alternative is to use BAdI MD_PLDORD_CHANGE to implement your own logic and define when the creation of planned orders will be allowed or not.

BR
Caetano

Answers (2)

Answers (2)

0 Kudos

Hi All,

Thanks you for Suggestion..

I was checking, if we have any functionality available in standard SAP.

Thanks you all..

BR

Balaji

former_member189817
Active Contributor
0 Kudos

Hello

It can be controlled only via authorization.

Regards,

Velmurugan S