Project Scheduling on Actual dates of Activity

Former Member
0 Kudos

Dear All,

Can we schedule a Project after actual Confirmation of Internal Activity.

Scenario: I have a project with start date 01.01.2014 and end date 31.12.2016. with some Activities with Relationship and Scheduled.

                      Basic Start Date        Basic Finish date      Actual Start Date           Actual Finish Date

Activity 1          01.01.2014               15.01.2014               01.01.2014                    15.01.2014

Activity 2          10.01.2014               20.01.2014               10.01.2015                    20.01.2015

due to some reason there are a Delay of 1 year in the Schedule. Now  i want that further Activities be scheduled According to the Actual Start Date of Second Activity. is is possible in Standard system. or what is the Procedure to adopt this.

Thanks

Govind

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If your activities are linked together through relationships, scheduling can automatically derive new dates based on actual dates of preceding activity

Answers (3)

Answers (3)

Former Member
0 Kudos

Answered.

Thanks for your valuable Replies.

Govind

kenmelching
Active Contributor
0 Kudos

Make sure you use bottom up scheduling.  SAP's scheduling algorithm uses Actual Dates as "anchors" and will schedule in relation to them.

Former Member
0 Kudos

Dear Govind,

Yes there are possibilities

Please look into the help

http://help.sap.com/saphelp_erp60_sp/helpdata/en/24/73b65334e6b54ce10000000a174cb4/content.htm?frame...

This will give you the complete view on scheduling

Hope this helps

Regards

Vittal