on 10-21-2015 7:27 AM
we are in sale order based costing. when we create cost estimate system is not showing any activity type. it shows only the cost of raw materials. activities are assigned in cost component structure and manual planning kp26 is done correctly. activities are also assigned in work center in costing tab.
Thanks a lot all of you for your cooperation.
issue resolved. problem was on pp side. routing shows activity correctly but not capturing the figures, anyways, the pp guy resolved it.
points assigned to everyone for your cooperation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check your valuation variant in costing variant whether proper routing id is selected
kamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.