on 10-20-2015 8:21 PM
Dear Team,
Can anyone please give me some idea on how to configure the connectors to point to the ECC server from HUB MDG System; so that the open PO/PR's can be displayed during a material change.
Any help would be sincerely appreciated.
Regards,
Tushar.
Hi Tushar,
That is maintained in the search connector definition.
SPRO --> Logistics General --> PLM --> PLM Web user interface --> Business Context viewer --> Search Integration --> Define Searc Connector
Or use SM31 on table Table: /bcv/c_sesysr
The open PO is defined as BAPI Search connnector
Cheers,
Henk.