Detailed computation of Cost Estimate for Direct Labor, Indirect Labor, Overhead etc.

In KP26 we maintained the following activity price,

Costing Lot size: 10,000

For the routing display (ca03) we maintained the ff:

Base Quantity 10,000 pc

Activity type:

Labor                     1 Hour

FSD                     10,000 pc

FSI                       10,000 pc

Depreciation        10,000 pc

Indirect Labor       10,000 pc

Machine (OOH)    10,000 pc

Scrap                     0

The resulting cost estimate for the above material is.

Question:  How to compute for the cost estimate for each activity type?

Main Material?Parts?Purchase of Products?Direct Labor, Labor Indirect, Fact supplies direct/indirect,depreciation, other overhead cost.

Thanks!

Former Member
Not what you were looking for? View more on this topic or Ask a question