Weekend is not affecting on due date calculation

Hi Everyone,

Hope you all are well.

I have set up calendar in company details and in same BP master data. I have checked the payment terms as well still dude date doesn't consider the weekends.

Just a quick question why weekend is not affecting on due date calculation in purchase invoice? Is it standard behaviour or I am missing something to set up in SAP?


Regards,


Vinod Memane

Former Member
Former Member replied

Hello Experts,

I got reply from SAP and they said it's a bug. They will publish note no : 2235700 for proper document and due date calculation. This functionality would be included in SAP 9.1 PL 11.

So sit back and wait for this bug to be corrected in new release.Rest assured.

Thanks,

Vinod Memane.