No Pur Req. without source of supply in SNP Optimizer

Former Member
0 Kudos

Hi,

We have a requirement where we do not want Pur Req (external) to be created if source of supply is not maintained when we run SNP optimizer.. Please provide your inputs on this.

We have a setting in version where we can maintain similar setting for planned order.

regards,

Mohit

Accepted Solutions (0)

Answers (1)

Answers (1)

satish_waghmare3
Active Contributor
0 Kudos

Hello Mohit,

You need a custom solution.

It can be done by using custom program to delete planned orders or Pur Req without source of supply. This program can be run immediately after SNP Heuristics and/or then again after Capacity Leveling.

You will require this BAPI :  BAPI_MOSRVAPS_DELEMULTI

Hope this will help.

Thank you

Satish Waghmare

kenneth_snyder
Active Contributor
0 Kudos

I am guessing that is not the requirement.

Are you trying to prevent optimizer from creating pur req's with source of supply blank when you have alternate sources of supply that are valid?

What if there is no valid source of supply?