on 10-17-2015 10:14 AM
Dear All,
how to define selection Variant in CNE2 (Tcode) collective Processing.
Actually I Create a Selection Variant for 20 Selected Projects. by tick on Only for background processing and save the variant. and then I run the project progress. but it give 0 in CNE5 project progress. while when i run CNE1 for these projects it shows progress.
Thanks
Govind
HI Govind
variant is nothing but its data saved in selection input screen, now let you know how to create this before executing the business transaction save the selection input then system will ask variant name and description give and save.
so purpose of variant creation multiple user can use simultaneously same variant.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Govind,
You need to check the Progress Version /Period are correct in the variant. May be the period is incorrect, kindly check it.
Did you execute the CNE1 with the same period for which you used in CNE2?
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Govind,
When you execute in foreground with the period, are you able to get the output.
You can just click the create icon next to Selection variant field in CNE2 and enter the projects you want to execute and save.
Choose the variant, version and period, execute and see whether you get the output.
Regards
Terence
Hi Terence,
I've executed the same procedure,
Create a variant>> select the 5 Projects >> Save this Variant.
then CNE2>> Select created Variant + Version + period + no tick on background & Test run.
then Cne5>> showing 0 progress.
while through Cne1>>update... i got Updated Progress.
i m not able to understand what is the issue.
Thanks
Govind
Hi Terence,
After testing with different projects, i got the different issue. actually when i run multiple projects in CNE2, only first project is get updated, others shows 0 Progress. i change the selection with different projects, but same first project of the list is updated and all others shows 0.
Thanks
Govind
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.