MRP Scenario issue with strategy type

Hi Experts,

Currently I am using MTO scenario and all PR is generating against particular sales order.

If i convert PR to PO sales order link continues

If i go GRN for PO same sales order link continues in stock level.

My problem is if any customer cancel Sales order suddenly i cant use this stock to any other sales order. We can do sales order to sales order but i cant track and do for lacs of components.

Now my requirement is i want use my raw material stock to any sales order. Is it possible to break the link from PR to PO.

Please suggest any other strategy or combo of strategy to execute this scenario successfully.

Thanks & Regards,

Mukundan